Majiwa Brokers Talks Between Affordable Housing Buyers, Contractors and Nairobi County

0
OPO

In Summary

  • Nairobi County Assembly’s Urban Planning and Housing Committee has initiated mediation between homebuyers, contractors and county officials over delayed housing projects.
  • Committee Chairman Geoffrey Majiwa says the parties have 14 days to agree on a settlement, with buyers having the option of receiving their houses or seeking refunds.
  • The committee will establish the causes of the delays and push for a clear timeline for completing the projects.

Nairobi County Assembly’s Urban Planning and Housing Committee Chairman Geoffrey Majiwa has moved to broker an agreement between Affordable Housing Programme beneficiaries, contractors and county officials following growing frustration over delayed housing projects.

The committee has taken up the matter after residents who paid for housing units complained of waiting for years without receiving their homes or getting satisfactory explanations from the County Executive on the status of the projects.

Majiwa said the committee had brought the parties together and secured a commitment to work towards an amicable resolution within 14 days.

He observed that the dispute had been prolonged by a communication breakdown between county officials and contractors, leaving homebuyers uncertain about the fate of their investments.

“Residents who purchased these units are saying they are not getting clear answers from the County Executive officers. The County Executive officers are also saying they are not getting clear answers from the contractors,” Majiwa said.

He explained that the committee would facilitate further discussions to establish the outstanding challenges, assess the contractors’ proposed completion timelines and agree on a solution that safeguards the interests of the buyers.

Majiwa added that residents who were unwilling to wait for the additional period requested by contractors should have the option of recovering their money instead of remaining tied to projects whose completion dates remain uncertain.

“If there is no availability of housing units, they are ready to take their money back. If they don’t want to wait for the period the contractors are requesting, we will ask the contractors to refund their money,” he said.

During the discussions, contractors attributed the delays to disruptions caused by the COVID-19 pandemic and the subsequent increase in the cost of construction materials, which they said had affected project implementation.

The committee chairman said the disagreements had created a stalemate that required intervention to bring the parties to a common position and provide homebuyers with certainty over their investments.

The committee is expected to complete its deliberations and issue a report within 14 days, detailing its findings and proposed recommendations.

On allegations that title deeds associated with the housing projects had been used to secure loans, Majiwa declined to comment, saying the claims needed verification before any conclusions could be reached.

He also addressed demands for the Ethics and Anti-Corruption Commission (EACC) and the Directorate of Criminal Investigations (DCI) to investigate the matter, saying the committee would first exercise its oversight mandate before determining whether the involvement of investigative agencies was necessary.

“Our work is to do oversight. When we think we need those agencies, we are the ones to involve them,” he said.